NR 440.76(12)(g)3.a.a. Calendar dates for which you did not collect the minimum amount of carbon feed rate data required under sub. (11) (e).
NR 440.76(12)(g)3.b.b. Reasons you did not collect the minimum data.
NR 440.76(12)(g)3.c.c. Corrective actions you took or are taking to get the required amount of data.
NR 440.76(12)(g)4.4. ‘Exclusions.’ You shall document each time you have excluded data from your calculation of average carbon feed rates and the reasons the data were excluded.
NR 440.76(12)(g)5.5. ‘Calendar dates.’ You shall include the calendar date on each record.
NR 440.76(13)(13)Reporting.
NR 440.76(13)(a)(a) What reports must I submit before I submit my notice of construction?
NR 440.76(13)(a)1.1. If you are required to submit an application for a construction permit under ch. NR 405 or 408, you shall submit the following 5 items by the date you submit your application:
NR 440.76(13)(a)1.a.a. Your draft materials separation plan, as specified in sub. (3) (d).
NR 440.76(13)(a)1.b.b. Your revised materials separation plan, as specified in sub. (3) (h) 3.
NR 440.76(13)(a)1.c.c. Your notice of the initial public meeting for your draft materials separation plan, as specified in sub. (3) (e) 2.
NR 440.76(13)(a)1.d.d. A transcript of the initial public meeting, as specified in sub. (3) (g) 6.
NR 440.76(13)(a)1.e.e. The document that summarizes your responses to the public comments you received during the initial public comment period, as specified in sub. (3) (h) 1.
NR 440.76(13)(a)2.2. If you are not required to submit an application for a construction permit under ch. NR 405 or 408, you shall submit the items in subd. 1. with your notice of construction.
NR 440.76(13)(b)(b) What must I include in my notice of construction and when must I submit it?
NR 440.76(13)(b)1.1. You shall include the following 10 items in your notice of construction:
NR 440.76(13)(b)1.a.a. A statement of your intent to construct the municipal waste combustion unit.
NR 440.76(13)(b)1.b.b. The planned initial startup date of your municipal waste combustion unit.
NR 440.76(13)(b)1.c.c. The types of fuels you plan to combust in your municipal waste combustion unit.
NR 440.76(13)(b)1.d.d. The capacity of your municipal waste combustion unit including supporting capacity calculations, as specified in sub. (15) (d) and (e).
NR 440.76(13)(b)1.e.e. Your siting analysis, as specified in sub. (4) (d).
NR 440.76(13)(b)1.f.f. Your final materials separation plan, as specified in sub. (3) (k) 2.
NR 440.76(13)(b)1.g.g. Your notice of the second public meeting (the siting analysis meeting) as specified in sub. (4) (e) 2.
NR 440.76(13)(b)1.h.h. A transcript of the second public meeting, as specified in sub. (4) (g) 4.
NR 440.76(13)(b)1.i.i. A copy of the document that summarizes your responses to the public comments you received during the second public comment period, as specified in sub. (4) (h) 1.
NR 440.76(13)(b)1.j.j. Your final siting analysis, as specified in sub. (4) (h) 3.
NR 440.76(13)(b)2.2. You shall submit your notice of construction no later than 30 days after you commence construction, reconstruction or modification of your municipal waste combustion unit.
NR 440.76(13)(c)(c) What reports must I submit after I submit my notice of construction and in what form?
NR 440.76(13)(c)1.1. You shall submit an initial report and annual reports, plus semiannual reports for any emission or parameter level that does not meet the limits specified in this section.