AB723-AA1,1,124
200.47
(2) (a) Except as provided in par. (b), all work done and all purchases
5of supplies and materials by the commission shall be by contract awarded to the
6lowest responsible bidder complying with the invitation to bid, if the work or
7purchase involves an expenditure of
$20,000 $50,000 or more. If the commission
8decides to proceed with construction of any sewer after plans and specifications for
9the sewer are completed and approved by the commission and by the department of
10natural resources under ch. 281, the commission shall advertise by a class 2 notice
11under ch. 985 for construction bids. All contracts and the awarding of contracts are
12subject to s. 66.0901.”.