March 1, 2023 - Introduced by Senators Feyen, Cowles and Quinn, cosponsored by
Representatives Plumer, Armstrong, Gundrum, Novak, O'Connor, Ohnstad
and Spiros. Referred to Committee on Government Operations, Elections and
Consumer Protection.
SB103,1,3 1An Act to amend 66.1105 (4) (gm) 4. c. and 66.1105 (6) (c); and to create 60.23
2(32) (bm), 66.1105 (2) (ak), 66.1105 (9) (a) 1m. and 66.1105 (21) of the statutes;
3relating to: developer-financed tax incremental districts.
Analysis by the Legislative Reference Bureau
This bill allows cities, villages, and certain towns to create developer-financed
tax incremental districts, which are excepted from the general rule that the
equalized value of taxable property of a new or amended tax incremental district
(TID) plus the value increment of all existing TIDs in a city or village may not exceed
12 percent of the total equalized value of taxable property in the city or village (12
percent rule) and the requirement that all areas of a TID be contiguous.
Under current law, cities and villages may use tax incremental financing (TIF)
to encourage development in the city or village. In general, under TIF, a city or
village pays for improvements in a TID and then collects tax moneys attributable to
all taxing jurisdictions on the increased property value in the TID for a certain period
of time to pay for the improvements. Ideally, after the period of time, the city or
village will have been repaid for its initial investment and the property tax base in
the TID will have permanently increased in value.
In general and in brief, a city or village makes use of TIF using the following
procedure:
1. The city or village designates an area as a TID and creates a project plan
laying out the expenditures that the city or village will make within the TID.

2. The Department of Revenue establishes the “base value” of the TID. This
value is the equalized value of all taxable property within the TID at the time of its
creation.
3. Each year thereafter, the “value increment” of the property within the TID
is determined by subtracting the base value from the current value of property
within the TID. The portion of taxes collected on any positive value increment is
collected by the city or village for use solely for the project costs of the TID. The taxes
collected by the city or village on positive value increments include taxes that would
have been collected by other taxing jurisdictions, such as counties or school districts,
were the TID not created.
4. Tax increments are collected until the city or village has recovered all of its
project costs or until the TID reaches its statutory termination date.
This bill allows a city or village to create a TID designated as a
developer-financed TID. To create a TID as a developer-financed TID, the local
legislative body must adopt a resolution making certain findings, and the joint
review board must approve the creation of the TID as a developer-financed TID. The
following are the findings that must be included in the resolution:
1. That all project costs of the TID will be paid directly from tax increments or
financed by a developer.
2. That the aggregate of all payments made to a developer providing financing
for a developer-financed TID will not exceed an amount equal to 90 percent of the
estimated tax increments to be generated by the TID.
Under the bill, developer-financed TIDs differ from other TIDs in that:
1. The 12 percent rule does not apply.
2. A developer-financed TID may contain noncontiguous areas.
3. All project costs must be paid directly from value increments generated by
the developer-financed TID or financed by the developer.
4. A city or village may share not more than 10 percent of the positive tax
increments allocated for a developer-financed TID in a year with any other TID
created by that city.
5. If a developer secures a loan from a private lender to finance project costs,
the city and the parties to the loan must agree that the debt is the responsibility of
the borrower and not the city.
6. The city may not issue tax incremental bonds or notes for financing a
developer-financed TID.
Under current law, towns have much more limited authority to use TIF than
do cities and villages. This bill allows towns that are adjacent to a city and that have
a population of more than 4,000 to create developer-financed TIDs if the project costs
are used solely for the construction of housing-related infrastructure.
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
SB103,1 1Section 1. 60.23 (32) (bm) of the statutes is created to read:
SB103,3,1
160.23 (32) (bm) 1. In this paragraph:
SB103,3,32 a. “Developer-financed tax incremental district” has the meaning given in s.
366.1105 (2) (ak).
SB103,3,54 b. “Town” means a town that is adjacent to a city and that has a population of
5more than 4,000.
SB103,3,116 2. Subject to subd. 3., a town may exercise all powers of cities under s. 66.1105
7to create a developer-financed tax incremental district. If the town board exercises
8the powers of a city under s. 66.1105, it is subject to the same duties as a common
9council that has acted under s. 66.1105 and the town is subject to the same duties and
10liabilities as a city that has acted under s. 66.1105 with regard to the
11developer-financed tax incremental district.
SB103,3,1412 3. The project costs for a developer-financed tax incremental district under this
13paragraph may include only expenditures for the construction of housing-related
14infrastructure, including highways and sewer and water facilities.
SB103,2 15Section 2. 66.1105 (2) (ak) of the statutes is created to read:
SB103,3,1716 66.1105 (2) (ak) “Developer-financed tax incremental district” means a tax
17incremental district created under sub. (21) (a).
SB103,3 18Section 3. 66.1105 (4) (gm) 4. c. of the statutes is amended to read:
SB103,4,619 66.1105 (4) (gm) 4. c. Except as provided in subs. (10) (c), (16) (d), (17), (18) (c)
203., (20) (b), and (20m) (d) 1., and (21), the equalized value of taxable property of the
21district plus the value increment of all existing districts does not exceed 12 percent
22of the total equalized value of taxable property within the city. In determining the
23equalized value of taxable property under this subd. 4. c. or sub. (17) (c), the
24department of revenue shall base its calculations on the most recent equalized value
25of taxable property of the district that is reported under s. 70.57 (1m) before the date

1on which the resolution under this paragraph is adopted. If the department of
2revenue determines that a local legislative body exceeds the 12 percent limit
3described in this subd. 4. c. or sub. (17) (c), the department shall notify the city of its
4noncompliance, in writing, not later than December 31 of the year in which the
5department receives the completed application or amendment forms described in
6sub. (5) (b).
SB103,4 7Section 4. 66.1105 (6) (c) of the statutes is amended to read:
SB103,5,48 66.1105 (6) (c) Except for tax increments allocated under par. (d), (dm), (e), (f),
9or (g), or erroneous reporting of value increments as described in par. (h), all tax
10increments received with respect to a tax incremental district shall, upon receipt by
11the city treasurer, be deposited into a special fund for that district. The city treasurer
12may deposit additional moneys into such fund pursuant to an appropriation by the
13common council. No moneys may be paid out of such fund except to pay project costs
14with respect to that district, to reimburse the city for such payments, to pay project
15costs of a district under par. (d), (dm), (e), (f), or (g) or sub. (21) (e), to pay property
16tax reimbursements as described under par. (h), or to satisfy claims of holders of
17bonds or notes issued with respect to such district. Subject to par. (d), (dm), (e), (f),
18or (g), moneys paid out of the fund to pay project costs with respect to a district may
19be paid out before or after the district is terminated under sub. (7). Subject to any
20agreement with bondholders, moneys in the fund may be temporarily invested in the
21same manner as other city funds if any investment earnings are applied to reduce
22project costs. After all project costs and all bonds and notes with respect to the
23district have been paid or the payment thereof provided for, subject to any agreement
24with bondholders, if there remain in the fund any moneys that are not allocated
25under par. (d), (dm), (e), (f), or (g), they shall be paid over to the treasurer of each

1county, school district or other tax levying municipality or to the general fund of the
2city in the amounts that belong to each respectively, having due regard for that
3portion of the moneys, if any, that represents tax increments not allocated to the city
4and that portion, if any, that represents voluntary deposits of the city into the fund.
SB103,5 5Section 5. 66.1105 (9) (a) 1m. of the statutes is created to read:
SB103,5,76 66.1105 (9) (a) 1m. Payment under sub. (21) (e) by the city from the special fund
7of a developer-financed tax incremental district;
SB103,6 8Section 6. 66.1105 (21) of the statutes is created to read:
SB103,5,119 66.1105 (21) Developer-financed tax incremental district. (a) A city may
10create a tax incremental district as a developer-financed tax incremental district if
11all of the following apply:
SB103,5,1212 1. The local legislative body adopts a resolution finding all of the following:
SB103,5,1513 a. That all project costs will be paid directly under sub. (9) (a) 1. or financed by
14a developer and that any financing obtained by a developer to finance project costs
15will be obtained through a private lender.
SB103,5,1916 b. That the aggregate of all payments made to a developer providing financing
17for a developer-financed tax incremental district will not exceed an amount equal
18to 90 percent of the estimated tax increments generated by the developer-financed
19tax incremental district.
SB103,5,2220 2. The clerk of the local legislative body certifies the resolution under subd. 1.
21and forwards a copy of the certified resolution to the department of revenue and the
22joint review board.
SB103,5,2423 3. The joint review board approves the creation of the tax incremental district
24as a developer-financed tax incremental district.
SB103,6,3
1(b) 1. All project costs for a developer-financed tax incremental district shall
2be paid directly under sub. (9) (a) 1. from tax increments generated by the
3developer-financed tax incremental district or financed by a developer.
SB103,6,54 2. All payments made by a city to a developer for financing a
5developer-financed tax incremental district shall be made under sub. (9) (a) 1.