This is the preview version of the Wisconsin State Legislature site.
Please see http://docs.legis.wisconsin.gov for the production version.
NR 346.05(2) (2) Except as provided in sub. (3), a fee of $1 shall be charged for the removal of bed material from natural lakes.
NR 346.05(3) (3) A fee will be charged for commercially valuable materials to be removed from the bed of a navigable lake. The fee will be equal to the royalty paid to owners of upland in the immediate vicinity of the natural lake in question for materials similar to those materials which are to be removed from the bed of a navigable lake. Current royalty prices for upland materials shall be obtained from commercial operators active in the project vicinity.
NR 346.05 History History: Cr. Register, September, 1980, No. 297, eff. 10-1-80.
NR 346.06 NR 346.06Bonding.
NR 346.06(1) (1) A performance or surety bond may be required for noncommercial removal projects regulated by this chapter. The bond amount shall be equal to the estimated cost for restoration of dangerous conditions or undesirable environmental conditions as determined by the department caused by incomplete or improper removal of bed materials from the project site or for removal in excess of volumes authorized. The maximum bond amount shall not exceed the estimated project cost. In determining the need for a bond the department shall consider the potential for creating unsafe conditions, environmental sensitivity of the project site, the qualifications of the applicant or contractor and potential for removal in excess of authority.
NR 346.06(2) (2) A performance or surety bond shall be required for commercial removal projects. The amount of the bond shall be determined by the department on the basis of the methods of removal, project site conditions, project size, project duration and the qualifications of the applicant or contractor.
NR 346.06 History History: Cr. Register, September, 1980, No. 297, eff. 10-1-80.
NR 346.07 NR 346.07Procedure.
NR 346.07(1) (1)Fee schedules.
NR 346.07(1)(a)(a) Application fees shall be submitted as a part of a complete application for a contract to remove material from the beds of natural lakes. The application fee shall be remitted to the applicant if the requested dredging contract is denied.
NR 346.07(1)(b) (b) Noncommercial fees shall be submitted by the applicant upon receipt of the contract from the department.
NR 346.07(1)(c) (c) Commercial removal fee shall be submitted in annual installments based upon the charge specified in the contract per cubic yard times the number of cubic yards of material removed under the contract for that calendar year. Quantities removed will be measured in its original position, computed by the method of average end areas, with no correction for curvature, or by the method of truncated prisms.
NR 346.07 Note Note: The methods of measuring the amounts of bed material removed during commercial projects were obtained from, “State of Wisconsin, Department of Transportation, Division of Highways, Standard Specifications for Road and Bridge Construction, Edition of 1975, Section 208.4 Method of Measurement", page 103.
NR 346.07 Note The following excerpt from, “Elementary Surveying, 5th Ed.", by Russell C. Brinker, pages 477 & 478, presents formulas for the methods of calculation specified by the Wisconsin department of transportation and incorporated in NR 346.
NR 346.07 Note End-areas formulas. The volume between 2 vertical cross sections A1 and A2 is equal to the average of the end areas multiplied by the horizontal distance L between them. Thus:
NR 346.07 Note Ve =L(A1 ) A2) cu. yd.
2 x 27
NR 346.07 Note This formula is approximate and gives answers which generally are slightly larger than the true prismoidal volumes. It is used in practice because of its simplicity. Increased accuracy is obtained by decreasing the distance L between the 2 sections. When the ground is irregular, cross-sections must be taken closer together.
NR 346.07 Note Prismoidal formula. The prismoidal formula applies to the volumes of all geometric solids which can be considered prismoids. Most earthwork volumes fit this classification but relatively few of them warrant the precision of the prismoidal formula, which is:
NR 346.07 Note Vp =L(A1 ) 4Am )A2)
6
NR 346.07 Note where Vp = volume;
A1 and A2 = areas of successive cross-sections taken in the field;
Am = area of a section midway between A1 and A2;
L = horizontal distance between A1 and A2.
NR 346.07(2) (2)Bonds.
NR 346.07(2)(a)(a) Bonds in the amount specified in the contract received by the applicant shall be secured by the applicant and submitted to the department of natural resources prior to any removal of material by the applicant on the contract issued by the department.
NR 346.07(2)(b) (b) Upon the successful completion of the dredging contract the applicant shall request a release from the bonding requirements. The department shall inspect the dredging site. If the department determines that the contract has been satisfactorily completed, the department will advise the applicant and bonding company that the bond may be canceled.
NR 346.07 History History: Cr. Register, September, 1980, No. 297, eff. 10-1-80.
NR 346.08 NR 346.08Enforcement.
NR 346.08(1) (1) If the department determines that the dredging contract has not been properly completed, it may initiate action to cause the applicant or applicant's agents to comply with the terms of the contract.
NR 346.08(2) (2) For dredging contracts with bonds where the applicant refuses to perform the requested remedial work, the department may require the bonding company or its agent to either perform the required remedial work or pay the amount of the bond to the department. The department, in its discretion, shall either complete the remedial work or contract for the completion of such work.
NR 346.08(3) (3) If the department determines that the dredging project has not been properly completed, and there is no bond, the department may initiate an abatement action pursuant to s. 30.03, Stats., to cause the applicant to restore the project site to comply with the terms of the contract, and forfeiture if the department thinks a forfeiture is appropriate.
NR 346.08 History History: Cr. Register, September, 1980, No. 297, eff. 10-1-80.
NR 346.09 NR 346.09Municipal dredging projects. Dredging from the beds of natural lakes by municipalities defined in s. 291.01 (12), Stats., may be done with no compensation to the state if the material dredged is for a municipal purpose and not for resale.
NR 346.09 History History: Cr. Register, September, 1980, No. 297, eff. 10-1-80 ; correction made under s. 13.93 (2m) (b) 7., Stats., Register January 2002 No. 553.
Loading...
Loading...
Published under s. 35.93, Stats. Updated on the first day of each month. Entire code is always current. The Register date on each page is the date the chapter was last published.